There have been 1 comment(s) made on this document:
  • David Case commented on 2012-05-31 15:51:48.82:
    The SDR process has gone thru several revisions with the changes proposed by the FCC addressing issues that needed clarification. Given that the FCC has allowed the TCB's to review this for well over a year, Cisco recommends that this current process be used to justify the removal of SDR approval from the PBA process at this time and we request the FCC to consider amending this to allow approval of SDR by TCB w/o the PBA process.

Note: It is important to understand that the staff guidance provided in the KDB is intended to assist the public in following Commission requirements and does not constitute rules. Accordingly, the guidance is not binding on the Commission and will not prevent the Commission from making a different decision in any matter that comes to its attention for resolution.