Please explain the purpose of operation: |
TrellisWare plans to perform LPTR units operate in full duplex mode in 2 days of testing on Feb. 5 and 6, 2025. Additional tests may be required, depending on NATOs needs.
The LPTR units operate in full duplex mode, which requires the use of two frequencies, one for each of the two directions of transmission between the two sites. For the frequency full-duplex link, the transmit frequency for one side of the link is taken from 5,930 – 6,109 MHz, and the transmit frequency for the other is taken from 6,182 – 6,361 MHz. TrellisWare plans to perform 2 days of testing on Feb. 5 and 6, 2025. Additional tests may be required, depending on NATOs needs.
The point of contact from the 29th NATO BLOS Comms Capability Team Meeting for this experiment is:
COL (Ret. US Army) Garth K. Winterle
DE: +49 152 02837561
US: +1 (443) 616-3126 (text preferred)
gwinterle@trellisware.com |